Lansdowne Park Construction Update – Week of July 15, 2013
Over the next couple of weeks residents will notice there will be some activity in the closed lane of Bank...
Over the next couple of weeks residents will notice there will be some activity in the closed lane of Bank...
This week there will be a few days of piling between the west side of the stadium and Bank Street...
The site will be closed on Monday, July 1 for Canada Day. Backfilling along the northern edge of the garage...
Activity will continue in the urban village and construction of the underground parking garage. The contractor for the building at...
Beginning on Thursday, June 20 the contractor will be backfilling along the Holmwood edge of the garage between Bank Street...
This week the contractor anticipates the construction of the next new building will begin. This building is referred to as...
The contractor plans to pour a large foundation slab on Saturday, June 15 on the west side of the Civic...
Construction activities will continue to be active in the urban village as work continues to build the garage on the...
Construction activities will continue next week at Lansdowne as additional columns and walls to support the underground parking garage are...
Ottawa’s transit challenge will be met with a highly functional route alignment that crosses the downtown core underground. From Tunney’s...