Lansdowne Park Construction Update – Week of December 8, 2013

Updated October 22 2026 · First published December 8 2013

XWhatsApp

Two activities next week will be visible along Holmwood. Early next week the contractor will be pouring concrete for the ramp into the garage that exits onto Holmwood. This will require a concrete truck to park on the street in order to access the ramp.

Also during the week precast concrete panels will be installed on the small building next to the Horticulture Building, near the Adelaide intersection. A truck and trailer will be parked on Holmwood in order to unload the panels.

This work will take about a week to complete. Normal traffic circulation will be maintained during the activity.