Today, Sun Nov 22Ottawa Christmas Market67’s vs Gatineau Olympiques 3:00 pm

Lansdowne 2.0

Lansdowne Park Construction Update – Week April 7, 2014

Updated October 22 2026 · First published April 7 2014

XWhatsApp
Tower cranes over the stadium construction site seen from the Rideau Canal pathway

This weekend the contractor will take down the tower crane at the office building along Bank Street, just in front of the Civic Centre.

The only remaining tower crane on the site will be at the condominium tower now under construction near the Bank Street Bridge.

With warmer weather beginning, the contractor is taking steps to reduce the amount of dirt on Bank Street from construction traffic.

They began sweeping the roadway this week, and will continue this activity as necessary.