Lansdowne Park Construction Update – Week of July 15, 2013

Updated October 22 2026 · First published July 12 2013

Yellow dump truck on a wet construction site in front of the old stadium grandstand

Over the next couple of weeks residents will notice there will be some activity in the closed lane of Bank Street in front of Lansdowne This work will not affect traffic.

Excavation for the parking garage along the most western edge of the site near Bank Street will continue for a couple weeks. Work will also begin for the large foundation of the building adjacent to the Bank Street Bridge.

Groundbreaking for the new urban park will occur on Monday. Following that the contractor will be bringing in equipment and setting up for the construction work.