The contractor will be working next week to lift and install the upper sections of the Veil – the wooden structure surrounding the south stands.
There will be several large cranes working in this area.
Large, precast concrete panels will begin to be installed on the office tower, located along Bank Street in front of the Civic Centre.
The work will be done from within the site though there may be some activity in the closed lane on Bank Street.
There will also likely be some excavation near Bank Street that may have minimal impact on traffic.