Lansdowne Park Construction Update, December 20, 2013

Lansdowne will remain open over the holiday period, except for statutory holidays. Between Christmas and New Year’s Day work will occur, but will be reduced. During this period, you may see some activity at the stadium, retail area and related to general site maintenance.

In January, full site operations will resume. Pouring concrete for the structure of the office tower along Bank Street in front of the Civic Centre will resume and will also begin for the condominium tower near the Bank Street Bridge. Work to fully enclose the retail buildings will continue in the New Year. At the stadium, construction of the Veil over the south stands and finishing inside the north stands will resume. There may also be some preparatory work in the area of the town homes that will front Holmwood late in January.

Full construction of the town homes is anticipated to start in late February, 2014.

Thank you Ottawa for your patience over the past year. Best wishes for a safe and happy holiday season.

Subscribe to the Lansdowne Blog!

REDBLACKS, Fury FC, & Ottawa 67's News, TD Place Events & Exclusive Deals!

   
 
Disclaimer: OttawaLansdownePark.com has No Affiliation with the City of Ottawa or the OSEG. We are a local blog providing news & sports updates on Lansdowne Park.