Lansdowne Park Construction Update – November 17, 2013

Installation of the precast concrete panels on the Holmwood side of the building at the corner of Bank and Holmwood will continue next week. A truck and trailer will be parked on Holmwood while the panels are unloaded.

Traffic flow will be maintained, but some of the parking spaces in the work area have been removed temporarily. This activity will take about a week to complete.

There will also be some activity near the Bank Street Bridge as the tower crane in the area is replaced late in the week.                                                                                       