Lansdowne Park Construction Update Week June 17, 2013

This week the contractor anticipates the construction of the next new building will begin. This building is referred to as ‘Building G’, and is located just north of the Civic Centre to the west of the Aberdeen Pavilion.

There will be lots of activity at the north side stands next week as the contractor starts to put the new roof panels into place early in the week. This operation will take a couple of weeks to complete.

Construction of the parking garage will continue along the Bank Street side of the site, particularly in front of the Civic Centre. Digging along the west edge of the site in front of the Civic Centre will proceed next week. The City and contractor are working together to reduce dust from this activity.

Source: City of Ottawa

   
 