Next week the contractor plans to begin work on the roof of the Horticulture Building, located across from the corner of Holmwood and O’Connor. This work is weather dependant, and access to the building will be from within the site.

Work will also start to build the main entrance way to the stadium from Bank Street. These activities will be conducted from within the closed traffic lane on Bank Street.

The contractor will also begin to build the structure of the residential tower next to the Bank Street Bridge, and there will be regular concrete pouring and finishing activities in this area.